August, 2005
Sewer System Evaluation and
Rehabilitation Program (SSERP)
Progress Report Through July 2005
SSERP
Summary
$181 million expended to date for evaluation
& repairs
Sewer System Basins are
divided into 10 basins for study, design and construction.
We have:
Inspected over 5.9 million feet of sanitary
sewer lines.
Rehabilitated more than 654,000 feet of sewer lines.
Inspected 22,200 sewer manholes.
Repaired or renovated 6,500 manholes.
Lakeview Basin
Last Sewer
Rehabilitation Project in the Lakeview Basin was Completed on
November 21, 2001.
Beat the Consent
Decree Requirement to Complete Construction before December 14,
2001.
Total Capital Cost: $21,590,000
CBD/FQ/WD Basin
Basin Construction
Started in October 2000.
Construction Started on Sewer/Fiber Pilot Project in April 2005.
On Schedule to Meet Consent Decree Requirement to Complete Construction by December 31, 2005.
Total Estimated Capital Cost: $19,000,000
Gentilly Basin
Last Sewer Rehabilitation Project in the Gentilly Basin was Completed on August 9, 2004.
Met the Consent Decree Requirement to Complete Construction by December 31, 2004.
Total Estimated Capital Cost: $27,000,000
Pipeline Rehabilitation in Gentilly Area Utilizing Slip Lining Method Uptown Basin
Uptown Basin
Construction Started in December 2002.
On Scheduled To Meet The Consent Decree Requirement
to Complete Construction By December 31, 2005.
Total Estimated Capital Cost: $28,200,000
Mid-City Basin
Design Completed in April 2005.
Construction started in June 2003.
On Schedule to meet the Consent Decree Requirement to Complete Construction by December 31, 2006.
Total Estimated Capital Cost: $40,500,000
Lower Ninth Ward Basin
Design - Ongoing
Construction Started in June 2004
On Schedule to Meet Consent Decree Requirement to Complete Construction by December 31, 2007
Total Estimated Capital Cost: $36,700,000
Carrollton Basin
Design - Ongoing
Construction Started in April 2005, Ahead of Schedule for Consent Decree Start Requirement of January 1, 2006.
Total Estimated Capital Cost: $43,500,000
New Orleans East Basin
Design Initiated in February 2005.
Construction to be Initiated
in 2006 in Order to Meet Consent Decree Start Requirement of January
1, 2007.
Total Estimated Capital Cost: $24,800,000
South Shore Basin
Study Completed in March 2005.
Design to be initiated in 2006.
Construction to be Initiated
in 2007 in Order to Meet Consent Decree Start Requirement of January
1, 2008.
Total Estimated Capital Cost: $12,100,000
Algiers Basin
Study to be Initiated in August 2005.
Total Estimated Capital Cost: $42,700,000
Capacity Upgrades
System Hydraulic Model -- Completed December 1999
Design
-- Design for Phase 1 Ongoing.
-- Design for Phase 2 Ongoing.
-- Design for Phase 3 Ongoing.
-- Design for Phase 4 Ongoing.
-- Design for Phase 5 Ongoing.
Construction
-- Construction for Phase 1 is Ongoing.