  SELA Project by Project

August, 2005


SOUTHEAST LOUISIANA (SELA) PROGRAM
ORLEANS PROJECTS

Progress Report Through July, 2005

 

D.P.S. No. 1
Project Start Date: December 17, 1998
Original Complete Date: July, 2001
Current Complete Date: Completed
Contractor: Pittman
Construction Cost: $12.2 M
State Funds Received: $0.0 M
Current % Complete: 100 %
On Current Schedule: Yes
Notes: This project is substantially complete. Contractor is working on last 1 punch list item.

Napoleon Avenue Canal

Project Start Date: September 8, 1999
Original Complete Date: September, 2002
Current Complete Date: Completed
Contractor: Iafrate
Construction Cost: $19.4 M
State Funds Received: $3.3 M
Current % Complete: 100 %
On Current Schedule: Yes
Notes: This project is substantially complete. Landscaping is the only item required to complete this project.

S. Claiborne - Nashville to Jena

Project Start Date: April 7, 2000
Original Complete Date: June, 2002
Current Complete Date: Completed
Contractor: Boh Bros.
Construction Cost: $9.5 M
State Funds Received: $2.0 M
Current % Complete: 100 %
On Current Schedule: Yes
Notes: This project is substantially complete. Landscaping is the only item required to complete this project.

S. Claiborne - Jena to Louisiana

Project Start Date: March 24, 2000
Original Complete Date: October, 2002
Current Complete Date: Completed
Contractor: Johnson Bros.
Construction Cost: $13.2 M
State Funds Received: $2.6 M
Current % Complete: 100 %
On Current Schedule: Yes
Notes: This project is substantially complete. Road work and landscaping are the only items required to complete this project.

Hollygrove Canals - R/R & Eagle

Project Start Date: August 4, 2000
Original Complete Date: May, 2003
Current Complete Date: Completed
Contractor: Iafrate
Construction Cost: $13.9 M
State Funds Received: $0.0 M
Current % Complete: 100%
On Current Schedule: Yes
Notes: This project is substantially complete. Landscaping is the only item required to complete this project.

Hollygrove Canals - Forshey & Dublin

Project Start Date: July 27, 2000
Original Complete Date: July, 2003
Current Complete Date: Completed
Contractor: B & K
Construction Cost: $14.3 M
State Funds Received: $0.0 M
Current % Complete: 100 %
On Current Schedule: Yes
Notes: This project is substantially complete. Landscaping is the only item required to complete this project.

Pritchard Place D. P. S.

Project Start Date: April 19, 2001
Original Complete Date: April, 2003
Current Complete Date: 2005
Contractor: Sopena Corp.
Construction Cost: $4.9 M
State Funds Received: $0.0 M
Current % Complete: 99 %
On Current Schedule: Yes
Notes: The pump station was declared substantially complete by the Corps in June 2004. The Contractor is working on punch list items. The Corps turned this station over to the S&WB in May 2005.

Dwyer Rd. D. P. S.

Project Start Date: September 20, 2000
Original Complete Date: August, 2003
Current Complete Date: June, 2006
Contractor: Pittman
Construction Cost: $13.6 M
State Funds Received: $1.2 M
Current % Complete: 52 %
On Current Schedule: Yes
Notes:

Dwyer Rd. D. P. S. Outfall Canal

Project Start Date: March 29, 2001
Original Complete Date: November, 2002
Current Complete Date: Completed
Contractor: C.R. Pittman
Construction Cost: $ 5.5 M
State Funds Received: $0.4 M
Current % Complete: 100%
On Current Schedule: Yes
Notes: This project is substantially complete.

Dwyer Intake Canal

Project Start Date: Unknown
Projected Complete Date: 2 1/2 years from start
Contractor: Not Awarded
Construction Cost: $18.5 M Est.
State Funds Received: $0.0 M
Current % Complete: N / A
On Schedule: N / A
Notes: A & E's 100% P & S submitted in late March 2003. The project may be advertised by the Corps of Engineers in mid 2005 depending on Federal funding.

Florida Avenue Canal I
(D.P.S. No. 19 to Mazant)

Project Start Date : Unknown
Projected Complete Date : 2 years from start
Contractor : Not Awarded
Construction Cost : $ 11.6 M Est.
State Funds Received : $ 1.6 M
Current % Complete : N/A
On Schedule : Yes / No N/A
Notes : A & E's 100% P & S submitted in October 2003. The project will not be advertised by the Corps of Engineers in 2005 due to the lack of Federal funding.

Palmetto Canal Obstruction Removal - Contract
Dublin St. Vehicular and S. Dupre Pedestrian Bridge Replacements

Project Start Date : 2nd Quarter 2004
Projected Complete Date : December 2005
Contractor : Boh Bros.
Construction Cost : $ 2.1 M Est.
State Funds Received : $ 0.0 M
Current % Complete : 72%
On Schedule : Yes / No Yes
Notes : Bids opened on 11-21-03. Notice to proceed on 02-17-04. Start of work November 2004.