| SSERP Progress Report |
| SSERP Summary |
$181 million expended to date for evaluation & repairs.
Sewer System Basins are divided into 10 basins for study, design and construction.
We have:
Inspected over 5.9 million feet of sanitary
sewer lines.
Rehabilitated more than 654,000 feet of sewer lines.
Inspected 22,200 sewer manholes.
Repaired or renovated 6,500 manholes.
|
 |
| Lakeview Basin |
Last Sewer Rehabilitation Project in the Lakeview Basin was Completed on November 21, 2001.
Beat the Consent Decree Requirement to Complete Construction before December 14, 2001.
Total Capital Cost: $21,590,000
|
 |
| CBD/FQ/WD Basin |
Basin Construction Started in October 2000.
Construction Started on Sewer/Fiber Pilot Project in April 2005.
On Schedule to Meet Consent Decree Requirement to Complete Construction by December
31, 2005.
Total Estimated Capital Cost: $19,000,000
|
 |
| Gentilly Basin |
Last Sewer Rehabilitation Project in the Gentilly Basin
was Completed on August 9, 2004. Met the Consent Decree Requirement to Complete
Construction by December 31, 2004.
Total Estimated Capital Cost: $27,000,000
|
 |
| Uptown Basin |
Construction Started in December 2002.
On Scheduled To Meet The Consent Decree Requirement to Complete Construction By
December 31, 2005.
Total Estimated Capital Cost: $28,200,000
|
 |
| Mid-City Basin |
Design Completed in April 2005.
Construction started in June 2003.
On Schedule to meet the Consent Decree Requirement to Complete Construction by
December 31, 2006.
Total Estimated Capital Cost: $40,500,000
|
 |
| Lower Ninth Ward Basin |
Design - Ongoing
Construction Started in June 2004
On Schedule to Meet Consent Decree Requirement to Complete Construction by December
31, 2007
Total Estimated Capital Cost: $36,700,000
|
 |
| Carrollton Basin |
Design - Ongoing
Construction Started in April 2005, Ahead of Schedule for Consent Decree Start
Requirement of January 1, 2006.
Total Estimated Capital Cost: $43,500,000
|
 |
| New Orleans East Basin |
Design Initiated in February 2005.
Construction to be Initiated in 2006 in Order to Meet Consent Decree Start
Requirement of January 1, 2007.
Total Estimated Capital Cost: $24,800,000
|
 |
| Algiers Basin |
Study to be Initiated in August 2005.
Total Estimated Capital Cost: $42,700,000
|
 |
| Capacity Upgrades |
System Hydraulic Model -- Completed December 1999
Design
-- Design for Phase 1 Ongoing.
-- Design for Phase 2 Ongoing.
-- Design for Phase 3 Ongoing.
-- Design for Phase 4 Ongoing.
-- Design for Phase 5 Ongoing.
Construction
-- Construction for Phase 1 is Ongoing.
For more information on SSERP click
here.
|
|
|